Express & Star

HS2 will ‘prove its worth’, boss Mark Wild says

He made the comments days after an influential group of MPs described HS2 as an example of ‘how not to run a major project’.

By contributor Neil Lancefield, PA Transport Correspondent
Published
HS2 CEO Mark Wild visits the Old Oak Common station site
HS2 will ‘prove its worth’, the boss of the company building the high-speed railway claimed (Jonathan Brady/PA)

HS2 will “prove its worth”, the boss of the company building the high-speed railway has claimed.

Mark Wild, chief executive of HS2, said the project has “great value, intrinsic value”.

He made the comments days after an influential group of MPs described HS2 as an example of “how not to run a major project”.

The Commons Public Accounts Committee warned last week that the cost of building the railway between London and the West Midlands “might be close to £80 billion”.

At an event on Tuesday to launch a study highlighting how the project has sparked economic growth in west London, Mr Wild said: “HS2 will prove its worth”.

He also insisted his ongoing “reset” of the programme will “break the cycle of this continuous drip-feed of bad news”.

Mr Wild, who joined HS2 Ltd at the start of December 2024, said: “The project has got itself into some difficulty, so my job is to reset it, put it back on track.

“It is true, we did the same thing in Crossrail, which should give us a lot of hope and benefit going forward.”

Mr Wild was hired to lead the Crossrail project – a new east-west railway line across London – in November 2018 after the project suffered major delays and ran overbudget.

He said he has “spent a lot of time thinking about the reasons” why there has been “such difficulty” with HS2.

He summarised the reasons as construction work starting with only “immature design”, awarding civil engineering contracts that were not “as effective as we thought”, and being “out of sequence” with civil engineering delays meaning later steps such as testing and putting trains on tracks cannot begin.

Rail minister Lord Hendy told the event – attended by west London business leaders – that the opening of HS2 will be “a day of national celebration”.

He continued: “It’s a timely reminder for not only those here, but those outside this room, that actually keeping the faith in HS2 – which is a project half built – is worth doing, and we need to celebrate what’s been achieved along the way too.”

A study commissioned by HS2 Ltd found the project is driving a £10 billion boost to west London.

Consultancy Arcadis found planning applications in the 1.5-mile radius around the site of HS2’s Old Oak Common station have increased by 22% since royal assent for the railway was granted in 2017.

HS2 project
An HS2 worker stands in front of tunnel boring machine Karen at the Old Oak Common station box site (Jonathan Brady/PA)

Mr Wild described west London as the capital’s “new property development hot spot”.

In relation to Old Oak Common station, Mr Wild said “nobody’s built on this scale”, and the opening will be a “catalytic event”.

He went on: “When we open Old Oak Common station, you will be 31 minutes from Birmingham International, the airport.

“You’ll be 42 minutes from the centre of Birmingham.

“(There will be) great connectivity to the West Country, Heathrow airport and, of course, into London on the Elizabeth line.