Express & Star

Bank vaults broke into as demolition work continues

A series of bank vaults in Birmingham city centre have been smashed into - but this wasn't the work of bank robbers.

Published
Last updated
A digger gets to work dismantling the vaults from above.
A digger gets to work dismantling the vaults from above.
Bank robbers would have had a job getting through these doors.

A series of bank vaults in Birmingham city centre have been smashed into - but this wasn't the work of bank robbers.

Underground vaults at the former Natwest Tower bank on Colmore Row, which once stored millions of pounds, have been brought down as the demolition of Natwest Tower presses forward.

Constructed from half a meter thick reinforced steel concrete walls, and doors made from 25cm thick steel, weighing more than a tonne, the old bank vaults are being removed as part of the demolition of the Natwest Tower.

Constructed from half a meter thick reinforced steel concrete walls, and doors made from 25cm thick steel, weighing more than a tonne, the old bank vaults, which have long been empty, are being removed as part of the demolition of the Natwest Tower.

Work to demolish the former bank building, which is being carried out by H Smith Engineering, started in 2015 and is due to be completed April.

Peter Graham, construction director at Sterling Property Ventures, said: “We’re reaching the final stages of the demolition programme.

"The removal of the bank vaults is one of the last significant milestones before we start to turn our attention to the next phase of the project, the construction of the new building, which we’re extremely excited about.”

When finished, 103 Colmore Row will comprise 224,000 sq ft of office space over 19 floors, plus 8,270 sq ft of leisure space, which includes a rooftop restaurant.

Eric Linden, European director at Rockspring, said: “It’s great to finally see the end in sight for the demolition phase of the project and we will soon start to see the new building rising from the ground."